Newport should finish operations in August 2008 (maybe this month?). It should then be moved to the closed category. Rmhermen (talk) 00:58, 5 July 2008 (UTC)[reply]

Updated. Neewport finished operation August 8, 2008. Rmhermen (talk) 20:13, 11 August 2008 (UTC)[reply]
Pine Bluff is scheduled to finish in December 2010 and should be moved then. Rmhermen (talk) 17:43, 8 November 2010 (UTC)[reply]
Anniston, Deseret and Umatilla are all scheduled to complete operations by March 2012 leaving only Pine Bluff and Pueblo which have not even started operations yet. Rmhermen (talk) 16:17, 27 February 2011 (UTC)[reply]
Only Pine Bluff and Pueblo remain - neither has started disposal operation yet so this template should be stable for quite some time now. Rmhermen (talk) 15:18, 2 February 2012 (UTC)[reply]