Work on the project's first stage, a link to [[Webb Dock]], was scheduled to begin in December 2015.<ref>{{cite press release | title = Western Distributor Project Gets The Green Light | publisher = Premier of Victoria | date = 8 December 2015 | url =http://www.premier.vic.gov.au/western-distributor-project-gets-the-green-light/ | access-date = 11 December 2015}}</ref>
Work on the project's first stage, a link to [[Webb Dock]], was scheduled to begin in December 2015.<ref>{{cite press release | title = Western Distributor Project Gets The Green Light | publisher = Premier of Victoria | date = 8 December 2015 | url =http://www.premier.vic.gov.au/western-distributor-project-gets-the-green-light/ | access-date = 11 December 2015}}</ref>


A 12-year extension to Transurban's tolling concession on CityLink, agreed as part of the proposed funding arrangement, has been estimated to provide Transurban with an additional $20 to $30 billion in tolling revenue.<ref>{{cite news | last1 =Schneiders| first1 =Ben|last2=Miller|first2=Royce | title =Toll bonanza | newspaper = [[The Age]] | location = Melbourne | pages = 1, 8| date = 6 February 2016|url = http://www.theage.com.au/business/citylink-users-to-be-slugged-tens-of-billions-under-andrews-government-plan-20160204-gmmahg}}</ref> The Deed Amendment to enable the tolling extension on CityLink was printed in the Government Gazette in December 2017.
A 12-year extension to Transurban's tolling concession on CityLink, agreed as part of the proposed funding arrangement, has been estimated to provide Transurban with an additional $20 to $30 billion in tolling revenue.<ref>{{cite news | last1 =Schneiders| first1 =Ben|last2=Miller|first2=Royce | title =Toll bonanza | newspaper = [[The Age]] | location = Melbourne | pages = 1, 8| date = 6 February 2016|url = http://www.theage.com.au/business/citylink-users-to-be-slugged-tens-of-billions-under-andrews-government-plan-20160204-gmmahg}}</ref> The Deed Amendment to enable the tolling extension on CityLink was printed in the Government Gazette in December 2017. In January 2020, it was reported the extension was for 10 years.<ref> [https://www.theage.com.au/national/victoria/premier-threatens-transurban-s-10-year-tolling-deal-over-west-gate-tunnel-debacle-20200130-p53w40.html Premier threatens Transurban's 10-year tolling deal over West Gate Tunnel debacle]</ref>


== Environment Effects Statement ==
== Environment Effects Statement ==

Revision as of 09:45, 30 January 2020

West Gate Tunnel

Western Distributor

General information
TypeFreeway  (Under construction)
Length5 km (3.1 mi)
Opened2022 (expected)
Major junctions
West end
  Footscray Road (State Route 32)
East end
Highway system

The West Gate Tunnel,[1] originally known as the Western Distributor, is a 5 kilometre toll road currently under construction in Melbourne, Australia, to link the West Gate Freeway at Yarraville with the Port of Melbourne and CityLink at Docklands via twin tunnels beneath Yarraville. The $6.7 billion project[2] was proposed by infrastructure company Transurban in 2014 as a means of alleviating congestion on the M1 corridor, providing a new river crossing as an alternative to the West Gate Bridge and moving trucks away from homes in the city's inner west. The freeway-standard link includes two tunnels with three lanes each that are approximately 4 km long outbound and 2.8 km long inbound, a new bridge over the Maribyrnong River, and an elevated road above Footscray Road. The project will also widen the West Gate Freeway from 8 to 12 lanes between the M80 Ring Road and the West Gate Bridge.[3]

The Victorian government announced in December 2015 it would proceed with the project. Planning approvals were granted in December 2017. Major construction of the tunnel and elevated tollway began in January 2018 and it is expected to be completed in 2022, although delays in late 2019 and early 2020 related to disposal of contaminated soil have cast doubt on that timing.[4][5][6]

Background and route

Heavy vehicles queue for traffic lights on Whitehall Street, Footscray, on a route that would be bypassed by the proposed West Gate Tunnel

According to state Treasurer Tim Pallas,the project was presented to then Victorian Labor opposition in 2014 by an engineering consultancy company as a "broad idea" by Transurban;[7] it was then kept secret until a public announcement by the Labor government in March 2015.[8] Transurban offered to pay two-thirds of the cost of construction in exchange for a 10 to 15-year extension of its CityLink toll contract. The remainder of the cost would be borne by federal funds.[9][10]

The Victorian government began assessing the proposal in March 2015 and announced in December that it would proceed. It said it would contribute $400 million of state funds and has proposed seeking funds previously committed by the federal government to the abandoned East West Link project.[11] The road project was proposed as an alternative to the government's $680 million West Gate Distributor, which in turn was designed to replace the western section of the East West Link.[12]

The proposed route has undergone some modification since plans were first released. The current plan is for eastbound traffic using the Western Distributor to exit the West Gate Freeway via a tunnel portal near Williamstown Road. Vehicles would emerge from the tunnel near Whitehall Street in Yarraville, then ascend to a new bridge over the Maribyrnong River and on to road elevated above Footscray Road, from where they would gain access to Swanson Dock at the Port of Melbourne, CityLink and the CBD via Docklands. A new link between the West Gate Freeway and Hyde Street would allow placarded trucks carrying dangerous loads such as fuel to directly access the freeway network for either eastbound or westbound travel rather than use local streets.[13]

One option presented in an early design of the project included a tunnel portal site located in Stony Creek Reserve, north of the freeway and between Hyde and Beverley streets. The move attracted criticism over the likelihood of additional noise, pollution and visual impact from the use of twin off-ramps connecting the portal to the freeway. The ramps and portal would have been within 100 metres of Yarraville homes. Critics claimed the proposed new location of the tunnel portal would result in the loss of part of the reserve and the creation of a "spaghetti junction" of overhead freeway ramps. A new community group, Concerned Locals of Yarraville, was formed and a petition started to oppose the move.[14]

In April 2017 the project was re-badged the West Gate Tunnel.[1]

Tolls

Toll fees for using the 5 km road and tunnel have been estimated at $3 for cars and $13 for trucks,[4] but Transurban says it may exempt trucks carrying dangerous placarded goods as an incentive to remove those trucks from local streets.[15]

The state government submitted the business case to Infrastructure Australia and the federal government in early December 2015 with a plea for commonwealth funding.[16] It announced the project will also include the widening of the West Gate Freeway from eight to 12 lanes between the M80 Ring Road and Williamstown Road and a $400 million widening of the Monash Freeway.[5] In April 2016 the state government said it would proceed without federal funding, instead allocating $1.4 billion to the project over four years.[17][18]

Work on the project's first stage, a link to Webb Dock, was scheduled to begin in December 2015.[19]

A 12-year extension to Transurban's tolling concession on CityLink, agreed as part of the proposed funding arrangement, has been estimated to provide Transurban with an additional $20 to $30 billion in tolling revenue.[20] The Deed Amendment to enable the tolling extension on CityLink was printed in the Government Gazette in December 2017. In January 2020, it was reported the extension was for 10 years.[21]

Environment Effects Statement

In May 2017 an Environment Effects Statement (EES) was released by the Victorian Government. It assesses environmental, social and health impacts of the project. The community was given 30 business days by the State Government to review the 10,000 page document.[22]

The directions hearing was held on Wednesday 19 July 2017 at the Footscray Community Arts Centre. The hearings commenced on 14 August 2017.

The Minister for Planning, Richard Wynne MP released an Assessment Report of the West Gate Tunnel Project, concluding the Environmental Effects Statement process on 27 November 2017.

Criticism

The project has been criticised by transport and urban planning experts, for overstating the benefits, increasing traffic in the inner city, and not considering better alternatives.[23] They have also criticised the lack of transparency in the planning process, and the lack of independent and democratic review.[24] In December 2017 the Coalition and the Greens vowed to block the project.[25]

Transport expert William McDougall gave evidence at a hearing of the Senate Inquiry into the Operation of existing and proposed toll roads on 3 August 2017. Mr McDougall was so alarmed by what he believed to be the weak economic case for the West Gate Tunnel when he was employed by the State Government to assess the proposal in 2015, that he personally contacted State Treasurer Tim Pallas to raise his concerns. He told the Senate inquiry he contacted the treasurer directly after unsuccessfully raising his concerns within the Department of Economic Development, Jobs, Transport and Resources. He was unexpectedly taken off the project about a week later. Mr McDougall said the Environment Effects Statement showed the issues he had raised with Treasurer Pallas had not been altered since he was removed from the project.[26]

Ryan Smith MP, the Opposition spokesperson for roads, has stated that "My personal position is that Transurban is gouging motorists and Daniel Andrews has backed himself into a corner – it's the worst negotiating position possible for taxpayers."[27]

Hobsons Bay City Council indicated the toll road would lead to a significant increase in truck traffic on its city’s streets, increased air pollution, and more noise. The Mayor, Cr Sandra Wilson, called for truck bans on Millers Road except for vehicles that start or terminate their journey at Brooklyn or Altona North, due to the EES traffic modelling showing that there would 7,000 extra truck movements per day on Millers Road. Cr Wilson said: “These functions will all undoubtedly be affected by the proposed increase of 7000 truck movements per day resulting from toll avoidance and the City of Maribyrnong truck bans.”[28] In December 2017, the University of Melbourne and the Royal Melbourne Institute of Technology's Centre for Urban Research released a report, West Gate Tunnel: Another Case of Tunnel Vision, criticising the Andrews Government for proceeding with the West Gate Tunnel and the North East Link, and calling on the Government to wait until after the 2018 election to proceed with both projects.[23]

Submissions on the Environment Effects Statement

The EES included modelling of traffic and congestion which demonstrated that even if the West Gate Tunnel is built, travel times along all existing routes, including the West Gate Freeway, the West Gate Bridge, Geelong Road, Buckley Street, Moore Street and CityLink during the morning and afternoon peaks would be worse in 2031 than they were in 2016. The modelling showed that the only route that would be quicker would be via the tolled tunnel, with a maximum saving of 8 minutes each way when compared to the slowest, non-tolled route.[29] These commute times were far worse than expected: the Andrews Labor Government had previously claimed that commuters in Werribee, Point Cook and Geelong would save 20 minutes each way.[27]

The EES indicated that the West Gate Tunnel would introduce thousands of more cars per day to residential streets in West Melbourne and North Melbourne. Modelling of traffic volumes in 2031 compared to a base case in 2031 of not building the West Gate Tunnel showed that, in North Melbourne and West Melbourne:[30]

  • Arden Street would carry 2,500 extra vehicles a day.
  • Queensberry Street would carry 1,500 extra vehicles per day.
  • Dryburgh Street would carry 3,500 extra vehicles per day.
  • Curzon Street would carry 2,000 extra vehicles per day.
  • Victoria Street would carry 3,000 extra vehicles per day.

In Docklands, Wurundjeri Way would be widened from 4 to 6 lanes, and is expected to carry another 9,000 vehicles per day. Docklands’ Harbour Esplanade, which is currently highly accommodating of pedestrians and cyclists, will have an extra 500 vehicles per day, slowing down trams in the morning and afternoon rush hours. These changes would Docklands into a throughway between the West Gate Tunnel and industrial areas in Port Melbourne and South Melbourne.[31][30]

The EES notes that there is a risk the toll road will have detrimental impacts on the local community. The EES suggests that the chance of noise resulting from vents and portals impacting upon cognitive function at schools, sleep disturbances causing an increase in hypertension, and increased risk of cardiovascular morbidity and premature mortality is 'medium'. The risk of noise resulting from the freeway component of the project impacting on cognition function at schools, sleep disturbance leading to an increase in hypertension, and increased risk of cardiovascular morbidity and premature mortality is ranked as 'high'. There is also a 'high' chance of residential houses and community facilities being subjected to dust and particles which will be created through disturbance of contaminated industrial sites during construction.[32] Yarra Trams, the concessionaire for Melbourne's tram system, made a submission that said the toll road, by putting so many new cars into North and West Melbourne, "may decrease" safe tram services because there was "an increased likelihood of tram-to-vehicle collisions" due to the "lack of road enforcement rules" in the area and "an increased number of uncontrolled turns across tram tracks".[33]

The hearings have also revealed that residents living near key construction sites for the West Gate Tunnel are likely to experience noise levels exceeding current ambient noise for up to four years while the toll road is built.[34] Furthermore, vehicular crashes on the West Gate Freeway are expected to double upon completion of the West Gate Tunnel from 61 to 117 a year by 2031. This is despite promises from the Andrews Labor Government to provide quicker and safer journeys.[35]

The Environment Effects Statement was assessed by Nathan Pittman, a PhD Candidate in Urban Planning at the University of Melbourne. Pittman found that the traffic modelling presented in the Environment Effects Statement of the West Gate Tunnel (WGT) is based on a practice that has a poor history of accuracy and rests on numerous assumptions that may not come to be. His conclusion was that:

The City of Melbourne conducted an analysis of the traffic modelling presented in the Environment Effects Statement in a 71-page report and found the WGT would:

  • Result in peak hour-like traffic conditions for 12–14 hours a day on four roads in North Melbourne;
  • Negatively affect tram performance across northern Melbourne; and,
  • Possibly undermine future tram improvements.

The report also stated the project would undermine future potential development of land five kilometres from the CBD, and remove 15,500 square metres of tree canopy.[36] The report also found the WGT would fail to improve access to the west, reduce truck traffic on residential streets and reduce congestion.[37]

See also

References

  1. ^ a b "Only The Best For The West With 6000 New Jobs". Premier of Victoria. 2 April 2017. Retrieved 2 April 2017.
  2. ^ Market-led Proposals (PDF), Victorian Auditor-General's Office, 2019, p. 52
  3. ^ "West Gate Tunnel Project design overview". West Gate Tunnel Project. Retrieved 15 January 2019.
  4. ^ a b White, Alex; Campbell, James; Devics, Alex (1 May 2015). "West Great Link". The Herald Sun. Melbourne. pp. 1, 4, 5.
  5. ^ a b White, Alex; Johnston, Matt; Ainsworth, Michelle (9 December 2015). "High toll for fast lane". Herald Sun. Melbourne. pp. 8, 9.
  6. ^ Willingham, Richard (9 December 2015). "New $5.5b toll road but who will pay for it?". The Age. Melbourne. pp. 2, 3.
  7. ^ Tim Pallas interviewed by Neil Mitchell, 3AW, 28 November 2019
  8. ^ Lucas, Clay (5 January 2016). "Environmental study for $5.5b road to start in weeks – but no final route set". The Age. Melbourne.
  9. ^ Gordon, Josh; Willingham, Richard (1 May 2015). "New toll road aimed at ending West Gate crush". The Age. Melbourne. pp. 2–3.
  10. ^ Carey, Adam (19 September 2015). "Transurban adds truck ramp to toll road design". The Age. Melbourne. p. 9.
  11. ^ Ainsworth, Michelle (22 September 2015). "Tunnel funnelled". The Herald Sun. Melbourne. p. 13.
  12. ^ Lucas, Clay (30 June 2015). "$5.5b freeway or truck ramps: decision by December". The Age. Melbourne. p. 8.
  13. ^ Johnston, Matt (18 September 2015). "Road to relief for inner west". The Herald Sun. Melbourne. p. 2.
  14. ^ Ainsworth, Michelle (28 September 2015). "Tollway war". The Herald Sun. Melbourne. p. 1,8.
  15. ^ Devics, Alex (30 September 2015). "Western Distributor: Trucks could be exempt from tolls". The Herald Sun. Melbourne.
  16. ^ "Road projects cash plea". The Herald Sun. Melbourne. 3 December 2015. p. 2.
  17. ^ "Victorian Government to fund Western Distributor toll road after Commonwealth refuses". ABC News. Melbourne. 14 April 2016.
  18. ^ Gordon, Josh (15 April 2016). "Victoria to go it alone on $5.5 billion Western Distributor project". The Age. Melbourne. pp. 4, 5.
  19. ^ "Western Distributor Project Gets The Green Light" (Press release). Premier of Victoria. 8 December 2015. Retrieved 11 December 2015.
  20. ^ Schneiders, Ben; Miller, Royce (6 February 2016). "Toll bonanza". The Age. Melbourne. pp. 1, 8.
  21. ^ Premier threatens Transurban's 10-year tolling deal over West Gate Tunnel debacle
  22. ^ "Environment Effects Statement – West Gate Tunnel Project". westgatetunnelproject.vic.gov.au. Retrieved 16 June 2017.
  23. ^ a b Jacks, Timna (8 December 2017). "Melbourne an international pariah on West Gate Tunnel, experts warn". The Age. Retrieved 8 December 2017.
  24. ^ Legacy, Crystal et al "Transurban’s West Gate tollway is a road into uncharted territory" in The Conversation, 19 December 2017
  25. ^ Willingham,Richard "Melbourne's West Gate Tunnel, cooked up by Labor with Transurban, deserves scrutiny", ABC, 13 December 2017
  26. ^ Lucas, Clay. "Expert cut from toll road project after warning Tim Pallas it did not stack up". The Age. Retrieved 7 August 2017.
  27. ^ a b Lucas, Clay; Carey, Adam (29 May 2017). "Transurban's tunnel will cut city-western suburbs commute by just eight minutes". The Age. Retrieved 16 June 2017.
  28. ^ Jefferson, Andrew (3 July 2017). "West Gate tunnel project concerns: Councils fear more trucks, noise and pollution". The Herald Sun. Retrieved 4 July 2017.
  29. ^ Figure 199 - M1 to central city AM Peak 2031 project travel times, p. 331, Transport Report A, Environment Effects Statementhttp://westgatetunnelproject.vic.gov.au/eesdocuments/
  30. ^ a b Figure 160, p. 254, Technical Report A – Transport, Part 1. GHD Pty Ltd., Environment Effects Statement http://westgatetunnelproject.vic.gov.au/eesdocuments/
  31. ^ pp. 5-29 - 5-30, Chapter 5 Project Description, Volume 1, Environmental Effects Statement, West Gate Tunnel http://westgatetunnelproject.vic.gov.au/eesdocuments/
  32. ^ Paul, Meaghan (4 June 2017). "The Westgate Tunnel project comes with a terrible hidden cost". The Sydney Morning Herald. Retrieved 16 June 2017.
  33. ^ Heffernan, Madeleine; Lucas, Clay. "West Gate Tunnel traffic increase a risk to trams, hearing told". The Age. Retrieved 29 August 2017.
  34. ^ Jefferson, Andrew (24 August 2017). "Residents told construction noise levels for West Gate Tunnel project to exceed standard for up to four years while toll road is built". The Herald Sun. Retrieved 29 August 2017.
  35. ^ Jefferson, Andrew (23 August 2017). "West Gate Freeway crashes set to double despite $6bn tunnel". The Herald Sun. Retrieved 29 August 2017.
  36. ^ Nightingale, Tom (30 June 2017). "West Gate Tunnel project 'a dog's breakfast', should be dumped, Melbourne councillor says". ABC. Retrieved 30 June 2017.
  37. ^ Royall, Ian (29 June 2017). "West Gate tunnel will create local traffic bedlam all day, every day: Melbourne City Council report". The Herald Sun. Retrieved 30 June 2017.